Churchyard Extension

The PCC are extremely grateful to Mr David Luxton, of Parsonage Farm, who is donating the land and helping with the work.

The legal fees are not insignificant, and any donations to help with these would be most appreciated.

Update 16th October 2025;

Delays upon delays. Professional ecological consultants, now, have to be engaged to satisfy planning requirements. This entails major cost and delay.

Mid 2026, start of works, now looks optimistic.

Mr David Simper is hard at work, bringing his legendary skills and patience to the task, for which the PCC is enormously grateful.

(Update 9th June 2025;)

Here is the MDDC pre-application advice (which was paid-for advice) Scroll the document page to read further.    

MDDC-Advice for Planning

Full application completed online on Tuesday 3rd June 2025

Planning Application sent in on 3 June 2025

Site Plan.

Site Location Plan

Planning Statement re local plan.

Local Planning Statement

Preliminary Ecological Appraisal.

Consultation re Private Water Supplies

Hedge removal details

Hedge Removal

Hydrogeological assessment

Hydrogeological assessment

Consultation re private water supplies

Consultation private water supplies

Ground engineering statement

Ground engineering statement

Heritage Statement

Heritage Statement (Gate)

Biodiversity net gains

Biodiversity net gains

Parking

Parking

 

Disbursements to date (6th June 2025)

MDDC pre-application advice receipt.

Pre-App-receipt.

MDDC Full planning application cost.

Full Application cost

Planning Rejection-6th June 2025

First rejection